Digitization project timeline calculator

From an image count and a measured capture rate to capture hours, working days, weeks and months.

Calculator

Fictional example values are filled in. Replace them with your own; results update as you type. Nothing you enter leaves your browser.

Measure this in the pilot. Bound volumes and glass plates are slower than loose sheets.

Results

Capture hours, including rework
420.0 hours
Capture days
70.0 days
Capture weeks
17.5 weeks
With assessment and pilot
19.5 weeks
Roughly
4.5 months

Capture is usually the longest stage, but text review and cataloging can overlap with it or run after it. Hours per day means hours at the camera or scanner, not hours on site.

“How long will it take?” is usually the first question a board or a funder asks. For most projects the answer starts with capture: how many images there are, how fast they can be made safely, and how many hours a week someone is at the camera or scanner. The calculator above turns those numbers into capture hours, working days, weeks and months, with time added for assessment and a pilot.

The formula in plain words

  1. Images to make = images × (1 + the share recaptured after quality control).
  2. Capture hours = images to make ÷ images captured per hour.
  3. Capture days = capture hours ÷ capture hours per day.
  4. Capture weeks = capture days ÷ capture days per week.
  5. With assessment and pilot = capture weeks + the weeks before full capture.
  6. Months = total weeks × 7 ÷ 30.44, the average number of days in a month.

Getting good inputs

  • Images. Count from your inventory: items × images per item, including backs and envelopes. The collection inventory worksheet keeps the counts by box and folder.
  • Images per hour. Measure this in a pilot rather than taking it from a brochure. The rate should include handling, positioning, checking and naming, not only exposures. Bound volumes and glass plates are slower than loose sheets, so run each kind of material separately and add the weeks.
  • Hours per day. This means hours at the camera or scanner, not hours on site. Setting up, imaging color targets, moving boxes and breaks all come out of the day, so six capture hours can fill a full working day.
  • Days per week. Allow for holidays, other duties and, for volunteer projects, the days people can actually come in.
  • Recapture share. The share of images redone after quality control. Your pilot gives a first figure; the QC sample size calculator shows how many images to check to measure it.
  • Assessment and pilot. The weeks before full capture starts: survey, specification, a pilot box and the decisions that follow it.

Reading the results

Use the weeks to set milestones and the months to talk with your board. The month figure converts weeks at the average month length; it does not skip holidays or closures.

Capture is usually the longest stage, but it is not the whole project. Text review and cataloging can overlap with capture or run after it. The digitization budget calculator gives the hours for those stages; divide them by the staff hours you have each week to see how long they run. How we work shows how the five stages (Assess, Capture, Read, Catalog, Return) fit together.

Limits

  • It schedules capture only. Text review, cataloging, delivery and the return of originals need their own time.
  • It assumes a steady rate from the first day. Real projects start slower while people learn the material.
  • It models one capture station. If two stations run at once, enter their combined rate, and only if both are staffed.
  • Transport, conservation treatment and rights questions can pause capture and are not included.

Worked example

Example (fictional). The Aster County Historical Society wants to digitize its manuscript and photograph collections, about 24,000 images in all. Timing during its pilot box showed 60 images an hour. The society can staff the capture station 6 hours a day, 4 days a week. About 5 percent of pilot images needed recapture after quality control, and assessment and the pilot take 2 weeks.

Step Arithmetic Result
Images to make 24,000 × 1.05 25,200
Capture hours, including rework 25,200 ÷ 60 420.0 hours
Capture days 420 ÷ 6 70.0 days
Capture weeks 70 ÷ 4 17.5 weeks
With assessment and pilot 17.5 + 2 19.5 weeks
Roughly 19.5 × 7 ÷ 30.44 4.5 months

The society plans its capture phase at about four and a half months and schedules cataloging to run alongside it.

Fitting a grant period

Grant-funded work has to finish inside a fixed period. As checked in November 2026, NEH’s Collections Stewardship program funds projects of up to three years. Build the schedule from measured rates, leave room for the slow material, and read each funder’s current guidelines for its dates. A collection assessment produces the counts, rates and timeline in the shape funders ask for, and the Reading Room’s planning and funding section covers schedules and budgets in more depth.

Send one box first.

A pilot box shows you the images, the recognized text and the catalog records before you commit a whole collection. Tell us what is in the box and what you want people to find.